🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

GAS · ERCOT

Schneider Gas Rice Phase 2

Schneider Gas Rice Phase 2 is a 113 MW gas request in interconnection study in the ERCOT interconnection queue, in Caldwell County, Texas.

Queue statusIn planning
  1. PlanningQueued Jul 2025 (current stage)
  2. ConsentedDec 2025 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2031 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
31INR0013
Grid region
ERCOT (Texas)
Developer
LCRA
Connection point (POI)
Double Tap 345kV #7042 Zorn - #7040 Austrop and #7042 Zorn - #9074 Lytton Springs
Location
Caldwell County, Texas
Technology
Gas: 113 MW
Total requested
113 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
29 July 2025
Agreement signed
19 December 2025
Proposed online date
May 2031

Location

Marker shows the centre of Caldwell County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Caldwell County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem