🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Oklahoma

SOLAR + STORAGE · SPP

Solar + storage project GEN-2020-010, Woodward County

Solar + storage project GEN-2020-010, Woodward County is a 140 MW solar + storage request in interconnection study in the SPP interconnection queue, in Woodward County, Oklahoma, connecting to WFEC.

Queue statusIn planning
  1. PlanningQueued Apr 2020 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2020-010
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WFEC
Connection point (POI)
Seiling-Taloga Substations 138kV
Location
Woodward County, Oklahoma
Technology
Solar: 140 MW · Battery
Total requested
140 MW
Service type
NRIS and ERIS
Study phase
FACILITY STUDY STAGE
Queue status
Active
Entered queue
8 April 2020
Proposed online date
June 2027

Location

Marker shows the centre of Woodward County; the queue data does not give exact sites.

Power plants in Oklahoma · Transmission lines in Oklahoma

Other requests in Woodward County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem