Solar + storage project GEN-2023-063, Rogers County

Solar + storage project GEN-2023-063, Rogers County is a 135 MW solar + storage request in interconnection study in the SPP interconnection queue, in Rogers County, Oklahoma, connecting to AEP.

Queue statusIn planning
  1. PlanningQueued Oct 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2023-063
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Catoosa - Owasso 88th 138 kV line
Location
Rogers County, Oklahoma
Technology
Solar: 135 MW · Battery
Total requested
135 MW
Service type
NRIS and ERIS
Study phase
FACILITY STUDY STAGE
Queue status
Active
Entered queue
2 October 2023
Proposed online date
December 2028

Location

Marker shows the centre of Rogers County; the queue data does not give exact sites.

Power plants in Oklahoma · Transmission lines in Oklahoma

Other requests in Rogers County