United States › Grid › Interconnection queues › Oklahoma

GAS · SPP

Gas project ERAS-2025-023, Rogers County

Gas project ERAS-2025-023, Rogers County is a 510 MW gas request in interconnection study in the SPP interconnection queue, in Rogers County, Oklahoma, connecting to AEP.

Queue statusIn planning
  1. PlanningQueued Oct 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
ERAS-2025-023
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Northeastern 345 kV Substation
Location
Rogers County, Oklahoma
Technology
Gas: 510 MW
Total requested
510 MW
Service type
NRIS and ERIS
Study phase
ERAS
Queue status
Active
Entered queue
2 October 2025
Proposed online date
December 2029

Location

Marker shows the centre of Rogers County; the queue data does not give exact sites.

Power plants in Oklahoma · Transmission lines in Oklahoma

Other requests in Rogers County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem