United States › Grid › Interconnection queues › Illinois

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in Illinois — page 8

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown42374.6 GW
Active in queue74.6 GW423 requests
Agreement signed7,430 MW51 requests
Withdrawn670115.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

423 requests · page 8 of 9
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project AH1-673, Cook County
Battery storage · Big Shoulders Storage LLC
85.0 MWIn study Cook, ILPJM Feb 2025
Battery storage project AG2-675, Rock Island County
Battery storage · Scout Solar DevCo LLC
80.0 MWIn study Rock Island, ILPJM Feb 2025target 2024
Solar project J1209, Saline County
Solar
80.0 MWAgreement signed Saline, ILMISO Apr 2019target 2023
Solar project J1208, Saline County
Solar
80.0 MWAgreement signed Saline, ILMISO Apr 2019target 2023
Battery storage project J2552, Rock Island County
Battery storage
80.0 MWIn study Rock Island, ILMISO Sep 2022target 2026
Hickory Wind
Onshore wind
78.7 MWPaused / redesign Putnam, ILPJM Oct 2016target 2025
Onshore wind project AI2-167, Logan County
Onshore wind
78.0 MWIn study Logan, ILPJM Mar 2023target 2024
Solar project J1475, Clark County
Solar
75.0 MWAgreement signed Clark, ILMISO Apr 20192024
Solar project J1180, Clark County
Solar
75.0 MWUnder construction Clark, ILMISO Mar 20182024
Battery storage project AH1-165, Will County
Battery storage · NRG Midwest Storage LLC
72.0 MWIn study Will, ILPJM Feb 2025target 2025
Solar project AI2-409, Dekalb County
Solar
72.0 MWIn study Dekalb, ILPJM Mar 2023target 2026
Solar project J1102, Logan County
Solar
70.0 MWUnder construction Logan, ILMISO Mar 20182022
Onshore wind project AI2-163, Mclean County
Onshore wind
68.8 MWIn study Mclean, ILPJM Mar 2023target 2025
Solar + storage project J1202, Randolph County
Solar + storage
68.4 MWAgreement signed Randolph, ILMISO Apr 2019target 2024
Onshore wind project J3976, Fayette County
Onshore wind
66.8 MWIn study Fayette, ILMISO Mar 2025target 2028
Solar project AI1-147, Dekalb County
Solar
64.0 MWIn study Dekalb, ILPJM Sep 2022target 2026
Battery storage project J2376, Shelby County
Battery storage
60.0 MWIn study Shelby, ILMISO Sep 2022target 2024
Solar project AI2-245, Woodford County
Solar
55.2 MWIn study Woodford, ILPJM Mar 2023target 2028
Solar project AG2-585, Kankakee County
Solar · Grand Marsh Solar 2, LLC
55.0 MWIn study Kankakee, ILPJM Mar 2025target 2024
Battery storage project AH2-372, Stephenson County
Battery storage
52.0 MWIn study Stephenson, ILPJM Mar 2022target 2028
Solar + storage project J1198, Jasper County
Solar + storage
51.8 MWAgreement signed Jasper, ILMISO Apr 2019target 2023
Solar + storage project AH2-199, Will County
Solar + storage
51.7 MWIn study Will, ILPJM Mar 2022target 2026
Zion Energy Center - BESS
Battery storage
50.0 MWAgreement signed Lake, ILPJM Nov 2019target 2027
Battery storage project AG2-061, Lasalle County
Battery storage · Aurora Solar LLC
50.0 MWIn study Lasalle, ILPJM Mar 2025target 2023
Top Crop Generating Facility
Battery storage · Blackstone Wind Farm, LLC
50.0 MWIn study Lasalle, ILPJM Mar 2020target 2023
Twin Groves Storage II
Battery storage
50.0 MWAgreement signed Mclean, ILPJM Mar 2020target 2028
Staley Solar
Solar
50.0 MWAgreement signed Kankakee, ILPJM Mar 2017target 2027
Broomstick Solar Energy Centergy Center
Solar
50.0 MWPaused / redesign Christian, ILPJM Mar 2018target 2028
Solar + storage project AH2-197, Mchenry County
Solar + storage
50.0 MWIn study Mchenry, ILPJM Mar 2022target 2025
Panther Grove Wind
Onshore wind
50.0 MWAgreement signed Woodford, ILPJM Mar 2019target 2027
Twin Groves Storage I
Battery storage
50.0 MWAgreement signed Mclean, ILPJM Mar 2020target 2028
Battery storage project J2974, Adams County
Battery storage
50.0 MWIn study Adams, ILMISO Sep 2022target 2026
Top Crop Generating Facility
Battery storage · Blackstone Wind Farm, LLC
50.0 MWIn study Lasalle, ILPJM Mar 2020target 2023
Battery storage project J3892, Sangamon County
Battery storage
50.0 MWIn study Sangamon, ILMISO Jan 2025target 2028
Battery storage project J2159, Clark County
Battery storage
50.0 MWIn study Clark, ILMISO Aug 2021target 2024
Solar project AI2-151, Logan County
Solar
48.0 MWIn study Logan, ILPJM Feb 2023target 2025
Solar project AI2-417, Dekalb County
Solar
48.0 MWIn study Dekalb, ILPJM Mar 2023target 2026
Onshore wind project J2312, Putnam County
Onshore wind
47.9 MWIn study Putnam, ILMISO Oct 2024target 2024
Battery storage project J1882, Tazewell County
Battery storage
45.0 MWIn study Tazewell, ILMISO Mar 2022target 2024
Solar + storage project J1201, Montgomery County
Solar + storage
44.2 MWAgreement signed Montgomery, ILMISO Apr 2019target 2024
Solar project AI2-060, Henry County
Solar
40.7 MWIn study Henry, ILPJM Feb 2023target 2024
Surplus; J1102
Other
40.0 MWIn study Logan, ILMISO Oct 2023target 2025
Solar project J3818, Shelby County
Solar
40.0 MWIn study Shelby, ILMISO Jun 2024target 2028
Battery storage project AI2-007, Kane County
Battery storage
40.0 MWIn study Kane, ILPJM Nov 2022target 2027
Rochelle Solar
Solar
40.0 MWAgreement signed Ogle, ILPJM Apr 2017target 2028
Gas project AH1-718, Lee County
Gas · Invenergy Nelson Expansion LLC
38.0 MWIn study Lee, ILPJM Apr 2025
Solar project AI2-014, Kankakee County
Solar
37.9 MWIn study Kankakee, ILPJM Nov 2022target 2026
Solar project J3188, Marshall County
Solar
35.0 MWIn study Marshall, ILMISO Sep 2022target 2023
Solar project J2982, Warren County
Solar
35.0 MWIn study Warren, ILMISO Sep 2022target 2023
Black Diamond Solar
Battery storage · Black Diamond Solar Power, LLC
30.0 MWIn study Christian, ILPJM Sep 2020target 2022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)