United States β€Ί Grid β€Ί Interconnection queues β€Ί Illinois

ONSHORE WIND Β· PJM

Hickory Wind

Hickory Wind is a 78.7 MW onshore wind request suspended in the PJM interconnection queue, in Putnam County, Illinois, connecting to ComEd.

Queue statusPaused / redesign
  1. PlanningQueued Oct 2016 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AC1-168
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ComEd
Connection point (POI)
Kewanee-Streator
Location
Putnam County, Illinois
Technology
Wind: 78.7 MW
Total requested
78.7 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Suspended
Entered queue
31 October 2016
Proposed online date
October 2025

Location

Marker shows the centre of Putnam County; the queue data does not give exact sites.

Power plants in Illinois Β· Transmission lines in Illinois

Other requests in Putnam County