United States βΊ Grid βΊ Interconnection queues βΊ Illinois
SOLAR + STORAGE Β· PJMSolar + storage project AH1-769, Putnam County
Solar + storage project AH1-769, Putnam County is a 105 MW solar + storage request withdrawn in the PJM interconnection queue, in Putnam County, Illinois, connecting to ComEd.
Queue statusWithdrawn / abandoned
- Planning (completed)
- Withdrawn / abandonedMay 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AH1-769
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ComEd
- Developer
- Marquis Solar LLC
- Location
- Putnam County, Illinois
- Technology
- Solar: 105 MW Β· Battery
- Total requested
- 105 MW
- Service type
- Network resource (NRIS)
- Study phase
- In Progress (unknown study)
- Queue status
- Withdrawn
- Proposed online date
- February 2028
- Withdrawn
- May 2025
Location
Marker shows the centre of Putnam County; the queue data does not give exact sites.
Other requests in Putnam County
- Solar + storage project J1200, Putnam CountySolar + storage Β· 24.2 MW Β· agreement signed
- Solar project J2554, Putnam CountySolar Β· 220 MW Β· in study
- Onshore wind project J2311, Putnam CountyOnshore wind Β· 145 MW Β· in study
- Battery storage project J2551, Putnam CountyBattery storage Β· 110 MW Β· in study
- Solar project J3899, Putnam CountySolar Β· 100 MW Β· in study
- Onshore wind project J2312, Putnam CountyOnshore wind Β· 47.9 MW Β· in study
- Hickory WindOnshore wind Β· 78.7 MW Β· suspended
- Onshore wind project AF1-318, Putnam CountyOnshore wind Β· 300 MW Β· withdrawn
- Onshore wind project T143, Putnam CountyOnshore wind Β· 250 MW Β· withdrawn
- Onshore wind project G914, Putnam CountyOnshore wind Β· 137 MW Β· withdrawn
- Battery storage project J3351, Putnam CountyBattery storage Β· 100 MW Β· withdrawn
- Solar project J3560, Putnam CountySolar Β· 20.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem