United States › Grid › Interconnection queues › California
OCTARY USA · INTERCONNECTION QUEUESInterconnection queue in California — page 8
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Wildhorse Energy Center Battery storage |
122 MW | In study |
| High Winds Storage Battery storage |
121 MW | In study |
| Excelsior Solar (Fka: Burford Five Points) Solar + storage |
120 MW | Agreement signed |
| Gonzaga Hybrid Wind + storage |
115 MW | Agreement signed |
| Reclaimed Wind Battery storage |
114 MW | Agreement signed |
| Serena Storage Battery storage |
114 MW | Agreement signed |
| Mulqueeney Ranch Wind Onshore wind |
114 MW | Agreement signed |
| Sienna Solar 2 Solar + storage |
112 MW | In study |
| Toland Renewable Energy Park Onshore wind |
108 MW | In study |
| Voyager Energy Storage Battery storage |
105 MW | In study |
| Ulua Battery storage |
105 MW | In study |
| Tioga Pass Battery storage |
103 MW | In study |
| Bonita Bateria Battery storage |
103 MW | In study |
| Oakdale Storage Battery storage |
103 MW | Agreement signed |
| Los Nietos Battery storage |
102 MW | Agreement signed |
| Cassia Battery storage |
102 MW | In study |
| Arges BESS Battery storage |
102 MW | In study |
| Denali Energy Storage Battery storage |
102 MW | Agreement signed |
| Pajaro Valley Storage Battery storage |
102 MW | In study |
| Kyan Solar Solar |
102 MW | Agreement signed |
| Droga Battery storage |
102 MW | In study |
| Tokay Storage Battery storage |
102 MW | Agreement signed |
| Double Springs Energy Storage Battery storage |
101 MW | Agreement signed |
| Sunbeam Storage Battery storage |
101 MW | Agreement signed |
| Eiger Energy Storage Battery storage |
101 MW | In study |
| Solar + storage project 2023-G4, Butte County Solar + storage |
100 MW | In study |
| Peaceful Hollow BESS Battery storage |
100 MW | Agreement signed |
| Solar + storage project GI-2023-171, Imperial County Solar + storage |
100 MW | In study |
| Keyhole Wind Onshore wind |
100 MW | Agreement signed |
| Golden Fields Solar Battery storage |
100 MW | Agreement signed |
| Sanborn Hybrid 4 Solar + storage |
100 MW | Agreement signed |
| Solar + storage project GI-2022-154, Imperial County Solar + storage |
100 MW | In study |
| Battery storage project GI-2023-166, Imperial County Battery storage |
100 MW | In study |
| Battery storage project Q110, Los Angeles County Battery storage |
100 MW | In study |
| Battery storage project 25, Sacramento County Battery storage |
100 MW | In study |
| Battery storage project GI-2022-153, Riverside County Battery storage |
100 MW | In study |
| Battery storage project Q109, Los Angeles County Battery storage |
100 MW | In study |
| Battery storage project 15, Sacramento County Battery storage |
100 MW | In study |
| Azalea Solar + storage |
99.3 MW | Agreement signed |
| Noosa Energy Storage Battery storage |
99.0 MW | Agreement signed |
| Solano 4 Wind Onshore wind |
92.4 MW | Agreement signed |
| Chalan Solar Solar + storage |
91.8 MW | Agreement signed |
| Fresno Cogeneration Expansion Project Gas |
91.8 MW | Agreement signed |
| Redwood Solar Farm Solar |
90.0 MW | Agreement signed |
| Battery storage project GI-2023-169, Imperial County Battery storage |
90.0 MW | In study |
| Solar + storage project GI-2021-148, Imperial County Solar + storage |
90.0 MW | In study |
| Sand Hill C Onshore wind |
84.3 MW | Agreement signed |
| Gonzaga Wind Farm Onshore wind |
80.0 MW | Agreement signed |
| Other project GI-2020-139, Riverside County Other |
80.0 MW | In study |
| Valetudo Energy Storage Battery storage |
79.6 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)