Interconnection queue in California — page 8

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown464179.2 GW
Active in queue179.2 GW464 requests
Agreement signed81.7 GW215 requests
Withdrawn2,138571.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

464 requests · page 8 of 10
ProjectCapacityStatusLocationRegionQueuedOnline
Wildhorse Energy Center
Battery storage
122 MWIn study Sonoma, CACAISO Apr 2021target 2030
High Winds Storage
Battery storage
121 MWIn study Solano, CACAISO Apr 2021target 2031
Excelsior Solar (Fka: Burford Five Points)
Solar + storage
120 MWAgreement signed Fresno, CACAISO Mar 20112016
Gonzaga Hybrid
Wind + storage
115 MWAgreement signed Merced, CACAISO Apr 2020target 2026
Reclaimed Wind
Battery storage
114 MWAgreement signed Alameda, CACAISO Apr 2018target 2026
Serena Storage
Battery storage
114 MWAgreement signed Kern, CACAISO Apr 2021target 2029
Mulqueeney Ranch Wind
Onshore wind
114 MWAgreement signed Alameda, CACAISO May 2016target 2026
Sienna Solar 2
Solar + storage
112 MWIn study San Bernardino, CACAISO Apr 2021target 2029
Toland Renewable Energy Park
Onshore wind
108 MWIn study Solano, CACAISO Apr 2023target 2029
Voyager Energy Storage
Battery storage
105 MWIn study Kern, CACAISO Apr 2023target 2027
Ulua
Battery storage
105 MWIn study Los Angeles, CACAISO Apr 2023target 2029
Tioga Pass
Battery storage
103 MWIn study San Joaquin, CACAISO Apr 2023target 2028
Bonita Bateria
Battery storage
103 MWIn study Orange, CACAISO Apr 2023target 2029
Oakdale Storage
Battery storage
103 MWAgreement signed Stanislaus, CACAISO Apr 2021target 2029
Los Nietos
Battery storage
102 MWAgreement signed Orange, CACAISO Apr 2021target 2031
Cassia
Battery storage
102 MWIn study San Joaquin, CACAISO Apr 2023target 2031
Arges BESS
Battery storage
102 MWIn study Solano, CACAISO Apr 2021target 2029
Denali Energy Storage
Battery storage
102 MWAgreement signed San Joaquin, CACAISO Apr 2020target 2028
Pajaro Valley Storage
Battery storage
102 MWIn study San Diego, CACAISO Apr 2021target 2030
Kyan Solar
Solar
102 MWAgreement signed Kern, CACAISO May 2016target 2027
Droga
Battery storage
102 MWIn study Merced, CACAISO Apr 2023target 2028
Tokay Storage
Battery storage
102 MWAgreement signed Santa Clara, CACAISO Apr 2021target 2030
Double Springs Energy Storage
Battery storage
101 MWAgreement signed Calaveras, CACAISO Apr 2021target 2029
Sunbeam Storage
Battery storage
101 MWAgreement signed San Mateo, CACAISO Apr 2021target 2034
Eiger Energy Storage
Battery storage
101 MWIn study Kern, CACAISO Apr 2021target 2032
Solar + storage project 2023-G4, Butte County
Solar + storage
100 MWIn study Butte, CAWest Aug 2023target 2028
Peaceful Hollow BESS
Battery storage
100 MWAgreement signed Fresno, CACAISO Apr 2021target 2028
Solar + storage project GI-2023-171, Imperial County
Solar + storage
100 MWIn study Imperial, CAWest Apr 2023target 2026
Keyhole Wind
Onshore wind
100 MWAgreement signed Kern, CACAISO Apr 2020target 2028
Golden Fields Solar
Battery storage
100 MWAgreement signed Kern, CACAISO Apr 2015target 2026
Sanborn Hybrid 4
Solar + storage
100 MWAgreement signed Kern, CACAISO Apr 2020target 2025
Solar + storage project GI-2022-154, Imperial County
Solar + storage
100 MWIn study Imperial, CAWest Feb 2022target 2024
Battery storage project GI-2023-166, Imperial County
Battery storage
100 MWIn study Imperial, CAWest Jan 2023target 2024
Battery storage project Q110, Los Angeles County
Battery storage
100 MWIn study Los Angeles, CAWest Jun 2024target 2027
Battery storage project 25, Sacramento County
Battery storage
100 MWIn study Sacramento, CAWest Aug 2022target 2027
Battery storage project GI-2022-153, Riverside County
Battery storage
100 MWIn study Riverside, CAWest Jan 2022target 2024
Battery storage project Q109, Los Angeles County
Battery storage
100 MWIn study Los Angeles, CAWest Jun 2024target 2027
Battery storage project 15, Sacramento County
Battery storage
100 MWIn study Sacramento, CAWest Dec 2021target 2027
Azalea
Solar + storage
99.3 MWAgreement signed Kern, CACAISO Apr 2018target 2025
Noosa Energy Storage
Battery storage
99.0 MWAgreement signed San Joaquin, CACAISO Apr 2019target 2029
Solano 4 Wind
Onshore wind
92.4 MWAgreement signed Solano, CACAISO Apr 2018target 2025
Chalan Solar
Solar + storage
91.8 MWAgreement signed Kern, CACAISO Apr 2018target 2026
Fresno Cogeneration Expansion Project
Gas
91.8 MWAgreement signed Fresno, CACAISO Mar 20052007
Redwood Solar Farm
Solar
90.0 MWAgreement signed Kern, CACAISO Mar 2011target 2024
Battery storage project GI-2023-169, Imperial County
Battery storage
90.0 MWIn study Imperial, CAWest Apr 2023target 2025
Solar + storage project GI-2021-148, Imperial County
Solar + storage
90.0 MWIn study Imperial, CAWest Nov 2021target 2027
Sand Hill C
Onshore wind
84.3 MWAgreement signed Alameda, CACAISO May 2017target 2027
Gonzaga Wind Farm
Onshore wind
80.0 MWAgreement signed Merced, CACAISO May 2017target 2026
Other project GI-2020-139, Riverside County
Other
80.0 MWIn study Riverside, CAWest Nov 2020target 2027
Valetudo Energy Storage
Battery storage
79.6 MWIn study Madera, CACAISO Apr 2021target 2028
Page 8 of 10

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)