United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in MISO (Midcontinent) — page 59

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3,261621.9 GW
Active in queue350.1 GW1,646 requests
Agreement signed28.1 GW187 requests
Withdrawn3,261621.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3,261 requests · page 59 of 66
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project J2779, Clinton County
Solar + storage
40.0 MWWithdrawn / abandoned Clinton, INMISO Sep 2022target 2025
Onshore wind project J574, Kandiyohi County
Onshore wind
40.0 MWWithdrawn / abandoned Kandiyohi, MNMISO May 2016target 2017
Battery storage project J1973, Champaign County
Battery storage
40.0 MWWithdrawn / abandoned Champaign, ILMISO Mar 2022target 2025
Solar project J1001, Lincoln County
Solar
40.0 MWWithdrawn / abandoned Lincoln, MNMISO Mar 2018target 2020
Onshore wind project H055, Redwood County
Onshore wind
40.0 MWWithdrawn / abandoned Redwood, MNMISO Jun 2008target 2011
Solar project J905, Pipestone County
Solar
40.0 MWWithdrawn / abandoned Pipestone, MNMISO Jun 2017target 2020
Onshore wind project H059, Nobles County
Onshore wind
40.0 MWWithdrawn / abandoned Nobles, MNMISO Jun 2008target 2011
Onshore wind project H068, Rice County
Onshore wind
40.0 MWWithdrawn / abandoned Rice, MNMISO Jun 2008target 2010
Solar project J784, Renville County
Solar
40.0 MWWithdrawn / abandoned Renville, MNMISO Nov 2016target 2018
Solar project J1600, Meade County
Solar
40.0 MWWithdrawn / abandoned Meade, KYMISO Jun 2020target 2022
Solar project J3740, Putnam County
Solar
40.0 MWWithdrawn / abandoned Putnam, INMISO Apr 2024target 2027
Battery storage project J2004, Fountain County
Battery storage
40.0 MWWithdrawn / abandoned Fountain, INMISO Mar 2022target 2025
Solar + storage project J2833, Wood County
Solar + storage
40.0 MWWithdrawn / abandoned Wood, WIMISO Sep 2022target 2025
Battery storage project J2320, Sunflower County
Battery storage
40.0 MWWithdrawn / abandoned Sunflower, MSMISO Sep 2021target 2023
Solar project J345, Waseca County
Solar
40.0 MWWithdrawn / abandoned Waseca, MNMISO May 2014target 2016
Coal project G105, Wayne County
Coal
40.0 MWWithdrawn / abandoned Wayne, MIMISO Jun 2001target 2003
Onshore wind project H056, Rice County
Onshore wind
40.0 MWWithdrawn / abandoned Rice, MNMISO Jun 2008target 2011
Onshore wind project H063, Mcleod County
Onshore wind
40.0 MWWithdrawn / abandoned Mcleod, MNMISO Jun 2008target 2011
Solar project J2347, Roscommon County
Solar
40.0 MWWithdrawn / abandoned Roscommon, MIMISO Sep 2022target 2025
Battery storage project J1230, Wadena County
Battery storage
40.0 MWWithdrawn / abandoned Wadena, MNMISO Apr 2019target 2023
Solar project J377, Bradley County
Solar
40.0 MWWithdrawn / abandoned Bradley, ARMISO Jul 2014
Onshore wind project H054, Redwood County
Onshore wind
40.0 MWWithdrawn / abandoned Redwood, MNMISO Jun 2008target 2011
Onshore wind project H067, Kandiyohi County
Onshore wind
40.0 MWWithdrawn / abandoned Kandiyohi, MNMISO Jun 2008target 2009
Other project J2373, Calcasieu Parish County
Other
40.0 MWWithdrawn / abandoned Calcasieu Parish, LAMISO Sep 2022target 2025
Onshore wind project J055, Deuel County
Onshore wind
40.0 MWWithdrawn / abandoned Deuel, SDMISO Jul 2009target 2011
Solar project J2085, Emmons County
Solar
40.0 MWWithdrawn / abandoned Emmons, NDMISO Nov 2021target 2024
Battery storage project J1439, Tunica County
Battery storage
40.0 MWWithdrawn / abandoned Tunica, MSMISO Apr 2019target 2022
Solar project J1098, Jackson County
Solar
40.0 MWWithdrawn / abandoned Jackson, MNMISO Mar 2018target 2022
Onshore wind project G576, Rock County
Onshore wind
40.0 MWWithdrawn / abandoned Rock, MNMISO Dec 2005target 2007
Onshore wind project J288, Kandiyohi County
Onshore wind
40.0 MWWithdrawn / abandoned Kandiyohi, MNMISO Jul 2013target 2019
Battery storage project J1975, Coles County
Battery storage
40.0 MWWithdrawn / abandoned Coles, ILMISO Mar 2022target 2025
Gas project J127, Wood County
Gas
40.0 MWWithdrawn / abandoned Wood, OHMISO Apr 2010
Onshore wind project J136, Fillmore County
Onshore wind
40.0 MWWithdrawn / abandoned Fillmore, MNMISO Feb 2009target 2013
Solar project J573, Washington County
Solar
40.0 MWWithdrawn / abandoned Washington, MOMISO May 2016target 2018
Onshore wind project J2067, Clay County
Onshore wind
39.4 MWWithdrawn / abandoned Clay, MNMISO Sep 2021target 2024
Onshore wind project J252, Audubon County
Onshore wind
39.1 MWWithdrawn / abandoned Audubon, IAMISO Sep 2012
Onshore wind project H064, Sibley County
Onshore wind
39.0 MWWithdrawn / abandoned Sibley, MNMISO Jun 2008target 2011
Onshore wind project J1761, Barnes County
Onshore wind
39.0 MWWithdrawn / abandoned Barnes, NDMISO Jun 2020target 2023
Onshore wind project G297, Edmunds County
Onshore wind
39.0 MWWithdrawn / abandoned Edmunds, SDMISO Feb 2003target 2008
Onshore wind project H061, Goodhue County
Onshore wind
39.0 MWWithdrawn / abandoned Goodhue, MNMISO Jun 2008target 2010
Onshore wind project J180, Goodhue County
Onshore wind
39.0 MWWithdrawn / abandoned Goodhue, MNMISO Nov 2010target 2012
Onshore wind project J1801, Story County
Onshore wind
39.0 MWWithdrawn / abandoned Story, IAMISO Jun 2020target 2023
Solar project J1784, Henry County
Solar
39.0 MWWithdrawn / abandoned Henry, INMISO Jun 2020target 2023
Onshore wind project J1728, Story County
Onshore wind
39.0 MWWithdrawn / abandoned Story, IAMISO Jun 2020target 2023
Onshore wind project H062, Goodhue County
Onshore wind
39.0 MWWithdrawn / abandoned Goodhue, MNMISO Jun 2008target 2011
Solar project J367, Goodhue County
Solar
39.0 MWWithdrawn / abandoned Goodhue, MNMISO May 2014target 2016
Onshore wind project J1244, Houghton County
Onshore wind
38.4 MWWithdrawn / abandoned Houghton, MIMISO Apr 2019target 2021
Solar + storage project J2782, Newton County
Solar + storage
38.0 MWWithdrawn / abandoned Newton, INMISO Sep 2022target 2025
Onshore wind project J930, Sioux County
Onshore wind
38.0 MWWithdrawn / abandoned Sioux, IAMISO Jun 2017target 2019
Onshore wind project J939, Wright County
Onshore wind
38.0 MWWithdrawn / abandoned Wright, IAMISO Jun 2017target 2019
Page 59 of 66

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)