Onshore wind project H067, Kandiyohi County

Onshore wind project H067, Kandiyohi County is a 40.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Kandiyohi County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2008 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. ConsentedApr 2011 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
H067
Grid region
MISO (Midcontinent)
Connection point (POI)
GRE Atwater 69 kV Substation
Location
Kandiyohi County, Minnesota
Technology
Wind: 40.0 MW
Total requested
40.0 MW
Study phase
Network Upgrade
Queue status
Withdrawn
Entered queue
17 June 2008
Agreement signed
20 April 2011
Proposed online date
December 2009

Location

Marker shows the centre of Kandiyohi County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Kandiyohi County