United States βΊ Grid βΊ Interconnection queues βΊ North Dakota
SOLAR Β· MISOSolar project J2085, Emmons County
Solar project J2085, Emmons County is a 40.0 MW solar request withdrawn in the MISO interconnection queue, in Emmons County, North Dakota, connecting to MONTANA-DAKOTA UTILITIES CO..
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2021 (completed)
- Withdrawn / abandonedOct 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J2085
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- MONTANA-DAKOTA UTILITIES CO.
- Connection point (POI)
- Linton NW 115 kV (radial to Wishek 115 kV)
- Location
- Emmons County, North Dakota
- Technology
- Solar: 40.0 MW
- Total requested
- 40.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 3; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 1 November 2021
- Proposed online date
- November 2024
- Withdrawn
- October 2025
Location
Marker shows the centre of Emmons County; the queue data does not give exact sites.
Power plants in North Dakota Β· Transmission lines in North Dakota
Other requests in Emmons County
- Solar project J4077, Emmons CountySolar Β· 45.0 MW Β· in study
- Solar project J4070, Emmons CountySolar Β· 40.0 MW Β· in study
- Onshore wind project J302, Emmons CountyOnshore wind Β· 101 MW Β· built
- Onshore wind project J503, Emmons CountyOnshore wind Β· 98.8 MW Β· built
- Gas project GI-1407, Emmons CountyGas Β· 800 MW Β· withdrawn
- Gas project GI-1408, Emmons CountyGas Β· 800 MW Β· withdrawn
- Gas project GI-1409, Emmons CountyGas Β· 100 MW Β· withdrawn
- Onshore wind project J779, Emmons CountyOnshore wind Β· 51.0 MW Β· withdrawn
- Onshore wind project J741, Emmons CountyOnshore wind Β· 51.0 MW Β· withdrawn
- Solar project J2084, Emmons CountySolar Β· 45.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem