πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

SOLAR Β· MISO

Solar project J2085, Emmons County

Solar project J2085, Emmons County is a 40.0 MW solar request withdrawn in the MISO interconnection queue, in Emmons County, North Dakota, connecting to MONTANA-DAKOTA UTILITIES CO..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2021 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2085
Grid region
MISO (Midcontinent)
Utility / transmission owner
MONTANA-DAKOTA UTILITIES CO.
Connection point (POI)
Linton NW 115 kV (radial to Wishek 115 kV)
Location
Emmons County, North Dakota
Technology
Solar: 40.0 MW
Total requested
40.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 3; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
1 November 2021
Proposed online date
November 2024
Withdrawn
October 2025

Location

Marker shows the centre of Emmons County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Emmons County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem