United States › Grid › Interconnection queues › North Dakota

SOLAR · MISO

Solar project J4077, Emmons County

Solar project J4077, Emmons County is a 45.0 MW solar request in interconnection study in the MISO interconnection queue, in Emmons County, North Dakota, connecting to MONTANA-DAKOTA UTILITIES CO..

Queue statusIn planning
  1. PlanningQueued Oct 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J4077
Grid region
MISO (Midcontinent)
Utility / transmission owner
MONTANA-DAKOTA UTILITIES CO.
Connection point (POI)
Linton NW
Location
Emmons County, North Dakota
Technology
Solar: 45.0 MW
Total requested
45.0 MW
Service type
Network resource (NRIS)
Queue status
Active
Entered queue
6 October 2025
Proposed online date
June 2030

Location

Marker shows the centre of Emmons County; the queue data does not give exact sites.

Power plants in North Dakota · Transmission lines in North Dakota

Other requests in Emmons County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem