United States β€Ί Grid β€Ί Interconnection queues β€Ί Missouri

SOLAR Β· MISO

Solar project J573, Washington County

Solar project J573, Washington County is a 40.0 MW solar request withdrawn in the MISO interconnection queue, in Washington County, Missouri.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2016 (completed)
  2. Withdrawn / abandonedJun 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J573
Grid region
MISO (Midcontinent)
Connection point (POI)
Belgrade 161kV
Location
Washington County, Missouri
Technology
Solar: 40.0 MW
Total requested
40.0 MW
Study phase
GIA
Queue status
Withdrawn
Entered queue
9 May 2016
Proposed online date
October 2018
Withdrawn
June 2017

Location

Marker shows the centre of Washington County; the queue data does not give exact sites.

Power plants in Missouri Β· Transmission lines in Missouri

Other requests in Washington County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem