United States βΊ Grid βΊ Interconnection queues βΊ Missouri
SOLAR Β· MISOSolar project J2239, Washington County
Solar project J2239, Washington County is a 100 MW solar request withdrawn in the MISO interconnection queue, in Washington County, Missouri, connecting to AMEREN MISSOURI.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2021 (completed)
- Withdrawn / abandonedOct 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J2239
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN MISSOURI
- Connection point (POI)
- Belgrade - Pilot Knob 161 kV
- Location
- Washington County, Missouri
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 12 August 2021
- Proposed online date
- October 2024
- Withdrawn
- October 2024
Location
Marker shows the centre of Washington County; the queue data does not give exact sites.
Other requests in Washington County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem