United States β€Ί Grid β€Ί Interconnection queues β€Ί Arkansas

SOLAR Β· MISO

Solar project J377, Bradley County

Solar project J377, Bradley County is a 40.0 MW solar request withdrawn in the MISO interconnection queue, in Bradley County, Arkansas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2014 (completed)
  2. Withdrawn / abandonedFeb 2015 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J377
Grid region
MISO (Midcontinent)
Connection point (POI)
MISO 115kV line in Zone 8 serving EAI Arkansas
Location
Bradley County, Arkansas
Technology
Solar: 40.0 MW
Total requested
40.0 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
14 July 2014
Withdrawn
February 2015

Location

Marker shows the centre of Bradley County; the queue data does not give exact sites.

Power plants in Arkansas Β· Transmission lines in Arkansas

Other requests in Bradley County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem