BATTERY STORAGE Β· MISO

Battery storage project J1230, Wadena County

Battery storage project J1230, Wadena County is a 40.0 MW battery storage request withdrawn in the MISO interconnection queue, in Wadena County, Minnesota, connecting to GREAT RIVER ENERGY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2019 (completed)
  2. Withdrawn / abandonedMar 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1230
Grid region
MISO (Midcontinent)
Utility / transmission owner
GREAT RIVER ENERGY
Connection point (POI)
Wing River- Riverton 230kV line
Location
Wadena County, Minnesota
Technology
Battery: 40.0 MW
Total requested
40.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
27 April 2019
Proposed online date
October 2023
Withdrawn
March 2021

Location

Marker shows the centre of Wadena County; the queue data does not give exact sites.