United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

SOLAR Β· MISO

Solar project J2433, Wadena County

Solar project J2433, Wadena County is a 150 MW solar request withdrawn in the MISO interconnection queue, in Wadena County, Minnesota, connecting to GREAT RIVER ENERGY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedMar 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2433
Grid region
MISO (Midcontinent)
Utility / transmission owner
GREAT RIVER ENERGY
Connection point (POI)
Wing River-Riverton 230kV
Location
Wadena County, Minnesota
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
14 September 2022
Proposed online date
October 2027
Withdrawn
March 2023

Location

Marker shows the centre of Wadena County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Wadena County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem