United States βΊ Grid βΊ Interconnection queues βΊ Minnesota
SOLAR Β· MISOSolar project J1597, Wadena County
Solar project J1597, Wadena County is a 75.0 MW solar request withdrawn in the MISO interconnection queue, in Wadena County, Minnesota, connecting to GREAT RIVER ENERGY.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2020 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1597
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- GREAT RIVER ENERGY
- Connection point (POI)
- Wing River Substation 230kV
- Location
- Wadena County, Minnesota
- Technology
- Solar: 75.0 MW
- Total requested
- 75.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 23 June 2020
- Proposed online date
- September 2023
Location
Marker shows the centre of Wadena County; the queue data does not give exact sites.