United States βΊ Grid βΊ Interconnection queues βΊ Iowa
ONSHORE WIND Β· MISOOnshore wind project J939, Wright County
Onshore wind project J939, Wright County is a 38.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Wright County, Iowa, connecting to MIDAMERICAN ENERGY COMPANY.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2017 (completed)
- Withdrawn / abandonedOct 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J939
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- MIDAMERICAN ENERGY COMPANY
- Connection point (POI)
- Clarion-Eagle Grove 69kV line
- Location
- Wright County, Iowa
- Technology
- Wind: 38.0 MW
- Total requested
- 38.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 16 June 2017
- Proposed online date
- September 2019
- Withdrawn
- October 2018
Location
Marker shows the centre of Wright County; the queue data does not give exact sites.
Other requests in Wright County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem