BATTERY STORAGE Β· MISO

Battery storage project J2004, Fountain County

Battery storage project J2004, Fountain County is a 40.0 MW battery storage request withdrawn in the MISO interconnection queue, in Fountain County, Indiana, connecting to DUKE ENERGY INDIANA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2022 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2004
Grid region
MISO (Midcontinent)
Utility / transmission owner
DUKE ENERGY INDIANA
Connection point (POI)
Other_
Location
Fountain County, Indiana
Technology
Battery: 40.0 MW
Total requested
40.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
23 March 2022
Proposed online date
October 2025
Withdrawn
December 2025

Location

Marker shows the centre of Fountain County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Fountain County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem