ONSHORE WIND Β· MISO

Onshore wind project H064, Sibley County

Onshore wind project H064, Sibley County is a 39.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Sibley County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2008 (completed)
  2. Withdrawn / abandonedOct 2008 (project stopped here)
  3. ConsentedOct 2008 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
H064
Grid region
MISO (Midcontinent)
Connection point (POI)
Crystal Foods Substation 69 kV
Location
Sibley County, Minnesota
Technology
Wind: 39.0 MW
Total requested
39.0 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
16 June 2008
Agreement signed
30 October 2008
Proposed online date
June 2011
Withdrawn
October 2008

Location

Marker shows the centre of Sibley County; the queue data does not give exact sites.