United States β€Ί Grid β€Ί Interconnection queues β€Ί Wisconsin

SOLAR + STORAGE Β· MISO

Solar + storage project J2833, Wood County

Solar + storage project J2833, Wood County is a 40.0 MW solar + storage request withdrawn in the MISO interconnection queue, in Wood County, Wisconsin, connecting to AMERICAN TRANSMISSION COMPANY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedJul 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2833
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMERICAN TRANSMISSION COMPANY
Connection point (POI)
Sigel - Auburndale Tap (Y-107) 69kV
Location
Wood County, Wisconsin
Technology
Solar: 40.0 MW Β· Battery
Total requested
40.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
12 September 2022
Proposed online date
March 2025
Withdrawn
July 2025

Location

Marker shows the centre of Wood County; the queue data does not give exact sites.

Power plants in Wisconsin Β· Transmission lines in Wisconsin

Other requests in Wood County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem