United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESInterconnection queue in the USA (2017 requests) โ page 5
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project 20 Solar |
74.5 MW | Paused / redesign |
| Solar project 306, Brevard County Solar ยท FPL |
74.5 MW | In study |
| Solar project 280, Hendry County Solar ยท FPL |
74.5 MW | In study |
| Solar project 289, Miami-Dade County Solar ยท FPL |
74.5 MW | In study |
| Sweet Sue Solar Solar |
74.0 MW | Agreement signed |
| Solar + storage project 333, Shelby County Solar + storage |
74.0 MW | Agreement signed |
| Solar project GEN-2017-057, Caddo Parish County Solar |
72.5 MW | Agreement signed |
| Solar project GEN-2017-231, Franklin County Solar |
72.5 MW | Agreement signed |
| Solar project GEN-2017-230, Lincoln County Solar |
72.5 MW | Agreement signed |
| Solar project GEN-2017-074, Mayes County Solar |
72.5 MW | Agreement signed |
| Solar project GEN-2017-073, Mayes County Solar |
72.5 MW | Agreement signed |
| Circleville Solar Energy Solar |
70.0 MW | Paused / redesign |
| Solar project 193, Levy County Solar ยท Origis Development LLC |
70.0 MW | In study |
| Solar project 48968, Chester County Solar |
69.8 MW | Agreement signed |
| Solar project QF17-068, Jefferson County Solar |
65.0 MW | Paused / redesign |
| Solar project GEN-2017-022, Wilson County Solar |
65.0 MW | Agreement signed |
| Angus Storage Battery storage |
63.0 MW | Paused / redesign |
| Columbia County 1 Solar ยท Hecate Energy Columbia County 1, LLC |
60.0 MW | In study |
| Agate Solar Solar |
60.0 MW | Paused / redesign |
| Sweetleaf Solar Solar |
60.0 MW | Paused / redesign |
| Chestnut Solar Solar |
60.0 MW | Paused / redesign |
| Solar project 314, Monroe County Solar |
60.0 MW | Agreement signed |
| Camino Solar Solar + storage |
58.3 MW | Agreement signed |
| Solar project GI-2017-5, Park County Solar |
54.3 MW | Agreement signed |
| Solar project GEN-2017-072, Payne County Solar |
52.2 MW | Agreement signed |
| Solar project GEN-2017-232, Bryan County Solar |
52.2 MW | Agreement signed |
| Solar project J791, Lamar County Solar |
52.0 MW | Agreement signed |
| Battery storage project GEN-2017-178, Garfield County Battery storage |
52.0 MW | Agreement signed |
| Solar project GEN-2017-173, Comanche County Solar |
50.0 MW | Agreement signed |
| Solar project IA-PNM-2017-07, Sandoval County Solar ยท NM Renewable Development |
50.0 MW | Agreement signed |
| Solar project JEA-Q007-PV, Duval County Solar |
50.0 MW | Agreement signed |
| Greenwood Solar Solar |
50.0 MW | Agreement signed |
| Solar project JEA-Q005-PV, Duval County Solar |
50.0 MW | Paused / redesign |
| Staley Solar Solar |
50.0 MW | Agreement signed |
| Solar project JEA-Q006-PV, Duval County Solar |
50.0 MW | Paused / redesign |
| Solar + storage project 905, Klamath County Solar + storage ยท Fresh Air Energy II, LLC |
50.0 MW | Paused / redesign |
| Solar project GEN-2017-172, Comanche County Solar |
50.0 MW | Agreement signed |
| Solar project JEA-Q004-PV, Duval County Solar |
50.0 MW | Paused / redesign |
| Battery storage project Company 155, Clark County Battery storage |
50.0 MW | Agreement signed |
| Solar project JEA-Q003-PV, Duval County Solar |
50.0 MW | Paused / redesign |
| NMRD Data Center IV Solar |
50.0 MW | Agreement signed |
| Watkins Glen Solar Solar ยท Watkins Glen Solar Energy Center, LLC |
50.0 MW | In study |
| Solar project IA-PNM-2017-06, Sandoval County Solar ยท NM Renewable Development |
50.0 MW | Agreement signed |
| Eaton OH Solar Solar |
49.9 MW | Agreement signed |
| Steubenville Solar Solar |
49.5 MW | Paused / redesign |
| Porter Mill Solar Solar |
45.8 MW | Agreement signed |
| Geothermal project Company HN, Washoe County Geothermal |
45.0 MW | Agreement signed |
| Solar + storage project 862, Box Elder County Solar + storage ยท Rocket Solar, LLC |
45.0 MW | Paused / redesign |
| Lueders Solar Solar ยท Innovative Solar 75 |
40.0 MW | In study |
| Rochelle Solar Solar |
40.0 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- SPP (Southwest Power Pool)66 ยท 11.8 GW
- West (non-ISO utilities)60 ยท 10.4 GW
- CAISO (California)17 ยท 8,678 MW
- ERCOT (Texas)36 ยท 5,724 MW
- MISO (Midcontinent)32 ยท 5,609 MW
- PJM (Mid-Atlantic, Midwest)44 ยท 4,774 MW
- Southeast (non-ISO utilities)28 ยท 2,517 MW
- ISO-NE (New England)3 ยท 831 MW
- NYISO (New York)6 ยท 749 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)