United States › Grid › Interconnection queues › Mississippi
SOLAR · MISOSolar project J791, Lamar County
Solar project J791, Lamar County is a 52.0 MW solar request with a signed interconnection agreement in the MISO interconnection queue, in Lamar County, Mississippi.
Queue statusConsented
- PlanningQueued Apr 2017 (completed)
- ConsentedMay 2017 (current stage)
- Construction (not yet reached)
- OperatingTarget Oct 2020 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J791
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Sumrall II Substation
- Location
- Lamar County, Mississippi
- Technology
- Solar: 52.0 MW
- Total requested
- 52.0 MW
- Study phase
- Out of Cycle
- Queue status
- Active
- Entered queue
- 24 April 2017
- Agreement signed
- 8 May 2017
- Proposed online date
- October 2020
Location
Marker shows the centre of Lamar County; the queue data does not give exact sites.
Power plants in Mississippi · Transmission lines in Mississippi
Other requests in Lamar County
- Solar project IC-986, Lamar CountySolar · 250 MW · suspended
- Solar project IC-1113, Lamar CountySolar · 200 MW · suspended
- Gas project J1249, Lamar CountyGas · 600 MW · built
- Solar project J473, Lamar CountySolar · 52.0 MW · built
- Sumrall SolarSolar · 50.0 MW · built
- Gas project IC-756, Lamar CountyGas · 550 MW · withdrawn
- Solar + storage project IC-1141, Lamar CountySolar + storage · 200 MW · withdrawn
- Solar + storage project J2321, Lamar CountySolar + storage · 180 MW · withdrawn
- Solar project IC-1029, Lamar CountySolar · 125 MW · withdrawn
- Solar project IC-682, Lamar CountySolar · 120 MW · withdrawn
- Solar project IC-1021, Lamar CountySolar · 80.0 MW · withdrawn
- Solar project IC-722, Lamar CountySolar · 55.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem