NMRD Data Center IV

NMRD Data Center IV is a 50.0 MW solar request with a signed interconnection agreement in the West interconnection queue, in Santa Fe County, New Mexico, connecting to Public Service Company of New Mexico.

Queue statusConsented
  1. PlanningQueued Jan 2017 (completed)
  2. ConsentedDec 2019 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2022 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
IA-PNM-2017-09
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company of New Mexico
Connection point (POI)
BA-ZIA 115 kV Line
Location
Santa Fe County, New Mexico
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
LGIA executed 12/30/2019.
Queue status
Active
Entered queue
31 January 2017
Agreement signed
30 December 2019
Proposed online date
November 2022

Location

Marker shows the centre of Santa Fe County; the queue data does not give exact sites.

Power plants in New Mexico · Transmission lines in New Mexico

Other requests in Santa Fe County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem