United States βΊ Grid βΊ Interconnection queues βΊ New Mexico
SOLAR + STORAGE Β· WESTSolar + storage project IA-PNM-2021-21, Santa Fe County
Solar + storage project IA-PNM-2021-21, Santa Fe County is a 199 MW solar + storage request withdrawn in the West interconnection queue, in Santa Fe County, New Mexico, connecting to Public Service Company of New Mexico.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2021 (completed)
- Withdrawn / abandonedMay 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IA-PNM-2021-21
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Public Service Company of New Mexico
- Connection point (POI)
- Norton 345 kv Line
- Location
- Santa Fe County, New Mexico
- Technology
- Solar: 199 MW Β· Battery
- Total requested
- 199 MW
- Service type
- Network resource (NRIS)
- Queue status
- Withdrawn
- Entered queue
- 29 October 2021
- Proposed online date
- June 2024
- Withdrawn
- May 2023
Location
Marker shows the centre of Santa Fe County; the queue data does not give exact sites.
Power plants in New Mexico Β· Transmission lines in New Mexico
Other requests in Santa Fe County
- Pentstemon SolarSolar + storage Β· 199 MW Β· agreement signed
- Globemallow SolarSolar + storage Β· 150 MW Β· agreement signed
- Solar + storage project IA-PNM-2019-05, Santa Fe CountySolar + storage Β· 96.0 MW Β· agreement signed
- NMRD Data Center IVSolar Β· 50.0 MW Β· agreement signed
- Solar project IA-PNM-2023-07, Santa Fe CountySolar Β· 300 MW Β· in study
- Solar + storage project IA-PNM-2023-30, Santa Fe CountySolar + storage Β· 250 MW Β· in study
- Solar project IA-PNM-2024-04, Santa Fe CountySolar Β· 230 MW Β· in study
- Solar + storage project IA-PNM-2023-22, Santa Fe CountySolar + storage Β· 200 MW Β· in study
- Solar + storage project IA-PNM-2022-03, Santa Fe CountySolar + storage Β· 100 MW Β· in study
- Solar project SGI-PNM-2014-05, Santa Fe CountySolar Β· 10.0 MW Β· built
- Onshore wind project IA-PNM-2017-16, Santa Fe CountyOnshore wind Β· 480 MW Β· withdrawn
- Solar project IA-PNM-2022-02, Santa Fe CountySolar Β· 220 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem