Solar + storage project IA-PNM-2021-21, Santa Fe County

Solar + storage project IA-PNM-2021-21, Santa Fe County is a 199 MW solar + storage request withdrawn in the West interconnection queue, in Santa Fe County, New Mexico, connecting to Public Service Company of New Mexico.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2021 (completed)
  2. Withdrawn / abandonedMay 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IA-PNM-2021-21
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company of New Mexico
Connection point (POI)
Norton 345 kv Line
Location
Santa Fe County, New Mexico
Technology
Solar: 199 MW Β· Battery
Total requested
199 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
29 October 2021
Proposed online date
June 2024
Withdrawn
May 2023

Location

Marker shows the centre of Santa Fe County; the queue data does not give exact sites.

Power plants in New Mexico Β· Transmission lines in New Mexico

Other requests in Santa Fe County