Solar project SGI-PNM-2014-05, Santa Fe County

Solar project SGI-PNM-2014-05, Santa Fe County is a 10.0 MW solar request built and operating in the West interconnection queue, in Santa Fe County, New Mexico, connecting to Public Service Company of New Mexico.

Queue statusOperating
  1. PlanningQueued Jul 2014 (completed)
  2. ConsentedApr 2015 (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
SGI-PNM-2014-05
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company of New Mexico
Connection point (POI)
PNM-GPD La Cienega State Pen Feeder 12
Location
Santa Fe County, New Mexico
Technology
Solar: 10.0 MW
Total requested
10.0 MW
Service type
Network resource (NRIS)
Study phase
SGIA executed 4/17/2015.
Queue status
Operational
Entered queue
29 July 2014
Agreement signed
17 April 2015

Location

Marker shows the centre of Santa Fe County; the queue data does not give exact sites.