United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESInterconnection queue in ERCOT (Texas) — page 5
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Panhandle Flagship Solar 1 Solar + storage · Panhandle Solar Group Operating Company LLC |
439 MW | Agreement signed |
| Buffalo Creek Solar · Lincoln Clean Energy Development |
439 MW | Agreement signed |
| Poco Trail Solar Solar · Eastern Trail Solar Center, LLC |
439 MW | In study |
| Magnet Storage Solar + storage · HyFuels Big Spring LLC |
427 MW | In study |
| Windecker Onshore wind · Windecker Energy LLC |
420 MW | In study |
| Whitehorse Wind Onshore wind · MESQUITE STAR SPECIAL LLC |
419 MW | Agreement signed |
| Gamay Energy Storage Battery storage · GAMAY ENERGY STORAGE LLC |
419 MW | Agreement signed |
| Sequoia II Solar Solar · Deville Solar LLC |
418 MW | Agreement signed |
| Bypass BESS II Battery storage · Bypass BESS II LLC |
416 MW | In study |
| Star Of Texas Solar Solar · BOULEVARD ASSOCIATES, LLC |
415 MW | In study |
| Green Holly Solar Solar · Copenhagen Infrastructure Partners Fund IV |
414 MW | Paused / redesign |
| BRP Artemis BESS Battery storage · BRP Artemis BESS LLC |
411 MW | In study |
| Dragan Solar Solar + storage · Hecate Comanche Solar LLC |
411 MW | In study |
| BRP Snowdon BESS Battery storage · BRP SNOWDON BESS LLC |
411 MW | In study |
| Western Flats Storage Solar + storage · Hecate Energy Point Mountain Solar Facility 1 LLC |
411 MW | In study |
| Western Flats Solar Solar + storage · Hecate Energy Point Mountain Solar Facility 1 LLC |
410 MW | In study |
| Silverton Solar Solar · NextEra Energy Interconnection Holdings, LLC |
410 MW | In study |
| BRP Mekong BESS Battery storage · BRP Mekong BESS LLC |
410 MW | In study |
| Operation Sunshine Storage Solar + storage · Duck Creek Storage, LLC |
410 MW | Agreement signed |
| Wilson BESS Battery storage · Dunamis BESS |
410 MW | In study |
| McCamey's Castle Battery Battery storage · Castle Storage, LLC |
410 MW | Agreement signed |
| Beacon Storage Battery storage · AES Distributed Energy, Inc |
409 MW | In study |
| Sigma Storage Battery storage · AES Distributed Energy, Inc |
408 MW | In study |
| Dragan Storage Solar + storage · Hecate Grid Dragan Storage LLC |
408 MW | In study |
| Grasshopper Solar Solar · Grasshopper Solar LLC |
408 MW | In study |
| Lund Storage Center 1 Battery storage · Lund Storage Center 1, LLC |
408 MW | In study |
| 18-Bravo BESS Battery storage · Scout Energy Management, LLC |
407 MW | In study |
| Caliche Mound Solar Solar · Tierra Blanco Solar LLC |
407 MW | Agreement signed |
| Claire BESS Battery storage · BRP Blue Topaz 3, LLC |
406 MW | In study |
| Compadre Solar Solar · Hill Solar I, LLC |
406 MW | Agreement signed |
| Ulysses Crossing Solar Solar |
405 MW | Paused / redesign |
| Two Step Solar Solar · Two Step Solar, LLC |
405 MW | In study |
| Big Rooter West Solar Solar + storage · Big Rooter West, LLC |
403 MW | Agreement signed |
| Hittson Creek Solar Solar + storage · 174 Power Global Properties |
403 MW | In study |
| Solarville Solar SLF Solar + storage · Ville Solar, LLC |
403 MW | In study |
| Bernice Energy Storage Battery storage · Bernice Energy Storage LLC |
403 MW | In study |
| Bluefox Solar 1 Solar · Industrial November Project LLC |
403 MW | In study |
| Merope BESS Battery storage · BRP Merope BESS LLC |
402 MW | In study |
| Smith Lake Solar DC Solar + storage · Smith Lake Solar |
402 MW | In study |
| Iron Belt Energy Storage Battery storage · Iron Belt Energy Storage Project, LLC |
402 MW | Agreement signed |
| Bluefox Solar 2 Solar · Industrial November Project LLC |
402 MW | In study |
| Infinium Solar Solar · Jackalope Flats Solar, LLC |
402 MW | In study |
| Bottom Grass Solar II Solar + storage · Flint Rock Solar Project, LLC |
402 MW | In study |
| Corruscant BESS Battery storage · AEU Battery Project III LLC |
402 MW | In study |
| Dorado Solar Solar · Enbridge Solar (Sequoia I), LLC |
401 MW | Agreement signed |
| Gridline Solar Solar · Big Lake Ranch LLC |
400 MW | In study |
| Vaquero 1 Wind Onshore wind · Enerverse |
400 MW | In study |
| Exergy Energy West Texas Natural Gas Reciprocating Power I Gas · August Partners LLC |
400 MW | In study |
| Biggs Solar Solar + storage · Biggs Solar Farm, LLC |
400 MW | In study |
| Springfield Solar Solar · BOULEVARD ASSOCIATES, LLC |
400 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)1,857 · 519.1 GW
- ERCOT (Texas)1,986 · 447.3 GW
- MISO (Midcontinent)1,646 · 350.1 GW
- CAISO (California)429 · 188.6 GW
- Southeast (non-ISO utilities)1,067 · 161.4 GW
- SPP (Southwest Power Pool)692 · 152.4 GW
- PJM (Mid-Atlantic, Midwest)1,248 · 140.4 GW
- NYISO (New York)190 · 27.1 GW
- ISO-NE (New England)72 · 14.6 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)