SOLAR · ERCOTSilverton Solar
Silverton Solar is a 410 MW solar request in interconnection study in the ERCOT interconnection queue, in Briscoe County, Texas.
Queue statusIn planning
- PlanningQueued Dec 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jul 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 28INR0023
- Grid region
- ERCOT (Texas)
- Developer
- NextEra Energy Interconnection Holdings, LLC
- Connection point (POI)
- Tap 345kV 23914 Tule Canyon - 79001 Cross_W1
- Location
- Briscoe County, Texas
- Technology
- Solar: 410 MW
- Total requested
- 410 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 4 December 2023
- Proposed online date
- July 2029
Location
Marker shows the centre of Briscoe County; the queue data does not give exact sites.
Other requests in Briscoe County
- Commodus WindOnshore wind · 641 MW · in study
- Commodus SolarSolar · 502 MW · in study
- BRP Snowdon BESSBattery storage · 411 MW · in study
- Silver Canyon Wind AOnshore wind · 200 MW · withdrawn
- Tecovas 1 WOnshore wind · 200 MW · withdrawn
- Tecovas 2 WOnshore wind · 200 MW · withdrawn
- Solar project GEN-2022-043, Briscoe CountySolar · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem