United States βΊ Grid βΊ Interconnection queues βΊ Texas
ONSHORE WIND Β· ERCOTTecovas 1 W
Tecovas 1 W is a 200 MW onshore wind request withdrawn in the ERCOT interconnection queue, in Briscoe County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2015 (completed)
- Withdrawn / abandonedDec 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 16INR0117
- Grid region
- ERCOT (Texas)
- Developer
- Engie
- Connection point (POI)
- 79503 Tule Canyon 345kV
- Location
- Briscoe County, Texas
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 22 June 2015
- Proposed online date
- October 2023
- Withdrawn
- December 2020
Location
Marker shows the centre of Briscoe County; the queue data does not give exact sites.
Other requests in Briscoe County
- Commodus WindOnshore wind Β· 641 MW Β· in study
- Commodus SolarSolar Β· 502 MW Β· in study
- BRP Snowdon BESSBattery storage Β· 411 MW Β· in study
- Silverton SolarSolar Β· 410 MW Β· in study
- Silver Canyon Wind AOnshore wind Β· 200 MW Β· withdrawn
- Tecovas 2 WOnshore wind Β· 200 MW Β· withdrawn
- Solar project GEN-2022-043, Briscoe CountySolar Β· 200 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem