United States › Grid › Interconnection queues › Texas
SOLAR + STORAGE · ERCOTDragan Storage
Dragan Storage is a 408 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Comanche County, Texas.
Queue statusIn planning
- PlanningQueued Aug 2020 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Feb 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 22INR0400
- Grid region
- ERCOT (Texas)
- Developer
- Hecate Grid Dragan Storage LLC
- Connection point (POI)
- 1440 Comanche 345kV
- Location
- Comanche County, Texas
- Technology
- Battery: 408 MW · Battery
- Total requested
- 408 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 21 August 2020
- Proposed online date
- February 2026
Location
Marker shows the centre of Comanche County; the queue data does not give exact sites.
Other requests in Comanche County
- Lamkin SolarSolar · 102 MW · agreement signed
- Comanche BESSBattery storage · 614 MW · in study
- Dragan SolarSolar + storage · 411 MW · in study
- Merope BESSBattery storage · 402 MW · in study
- Crios BESSBattery storage · 206 MW · in study
- BRP Triton BESSBattery storage · 205 MW · in study
- Saddle Horn Station BESS SLFSolar + storage · 177 MW · in study
- Saddle Horn Station Solar SLFSolar + storage · 175 MW · in study
- Darkwood SolarSolar + storage · 151 MW · in study
- Darkwood BESSSolar + storage · 151 MW · in study
- Paolo Sole Gustine SolarSolar · 40.3 MW · in study
- Spectrum SolarSolar · 400 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem