United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTLamkin Solar
Lamkin Solar is a 102 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Comanche County, Texas.
Queue statusConsented
- PlanningQueued Jun 2019 (completed)
- ConsentedMar 2025 (current stage)
- Construction (not yet reached)
- OperatingTarget Aug 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 22INR0220
- Grid region
- ERCOT (Texas)
- Developer
- Commanche Solar, LLC
- Connection point (POI)
- tap 69kV 258 Hamilton - 273 Gustine
- Location
- Comanche County, Texas
- Technology
- Solar: 102 MW
- Total requested
- 102 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 24 June 2019
- Agreement signed
- 6 March 2025
- Proposed online date
- August 2027
Location
Marker shows the centre of Comanche County; the queue data does not give exact sites.
Other requests in Comanche County
- Comanche BESSBattery storage · 614 MW · in study
- Dragan SolarSolar + storage · 411 MW · in study
- Dragan StorageSolar + storage · 408 MW · in study
- Merope BESSBattery storage · 402 MW · in study
- Crios BESSBattery storage · 206 MW · in study
- BRP Triton BESSBattery storage · 205 MW · in study
- Saddle Horn Station BESS SLFSolar + storage · 177 MW · in study
- Saddle Horn Station Solar SLFSolar + storage · 175 MW · in study
- Darkwood SolarSolar + storage · 151 MW · in study
- Darkwood BESSSolar + storage · 151 MW · in study
- Paolo Sole Gustine SolarSolar · 40.3 MW · in study
- Spectrum SolarSolar · 400 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem