United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Interconnection queue in the USA (2018 requests) โ€” page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown34867.1 GW
Active in queue67.1 GW348 requests
Agreement signed32.4 GW175 requests
Withdrawn1,424226.5 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

348 requests ยท page 3 of 7
ProjectCapacityStatusLocationRegionQueuedOnline
Las Camas 3
Solar + storage
203 MWAgreement signed Merced, CACAISO Apr 2018target 2027
Solar project GEN-2018-132, Pierce County
Solar
202 MWAgreement signed Pierce, NESPP Nov 2018target 2026
Onshore wind project GEN-2018-128, Sumner County
Onshore wind
200 MWAgreement signed Sumner, KSSPP Nov 2018target 2030
Rueter Solar
Solar
200 MWPaused / redesign Bosque, TXERCOT Sep 2018
Solar project J992, Cass County
Solar
200 MWUnder construction Cass, INMISO Mar 2018target 2023
Onshore wind project J1069, Jasper County
Onshore wind
200 MWUnder construction Jasper, INMISO Mar 2018target 2023
Solar + storage project Q270, Navajo County
Solar + storage
200 MWUnder construction Navajo, AZWest Mar 2018target 2021
Solar + storage project NC5-005, Clark County
Solar + storage
200 MWIn study Clark, NVWest May 2018target 2021
Onshore wind project J1115, Macon County
Onshore wind
200 MWUnder construction Macon, ILMISO Mar 2018target 2024
Battery storage project Q291, Maricopa County
Battery storage
200 MWIn study Maricopa, AZWest Sep 2018target 2023
Solar project J956, Ralls County
Solar
200 MWAgreement signed Ralls, MOMISO Mar 20182024
Desert Rose Solar
Solar
200 MWPaused / redesign Andrews, TXERCOT Jun 2018
Battery storage project GEN-2018-025, Washington County
Battery storage
200 MWPaused / redesign Washington, NESPP May 2018target 2028
Solar project J1107, Cape Girardeau County
Solar
200 MWUnder construction Cape Girardeau, MOMISO Mar 2018target 2023
Solar project J993, Boone County
Solar
200 MWUnder construction Boone, INMISO Mar 2018target 2023
Solar project J1007, Crittenden County
Solar
200 MWUnder construction Crittenden, ARMISO Mar 20182023
Solar + storage project Company IL, Washoe County
Solar + storage
200 MWAgreement signed Washoe, NVWest Mar 2018target 2027
Solar + storage project Q288, Maricopa County
Solar + storage
200 MWIn study Maricopa, AZWest Sep 2018target 2021
Onshore wind project J984, Gratiot County
Onshore wind
200 MWUnder construction Gratiot, MIMISO Mar 20182023
Solar project J1076, St. James Parish County
Solar
200 MWUnder construction St. James Parish, LAMISO Mar 2018target 2022
Battery storage project GEN-2018-033, Cass County
Battery storage
200 MWPaused / redesign Cass, NESPP May 2018target 2029
Kce NY 2
Battery storage ยท KCE NY 2, LLC
200 MWIn study Montgomery, NYNYISO Jan 2018target 2027
Battery storage project GEN-2018-028, Tulsa County
Battery storage
200 MWAgreement signed Tulsa, OKSPP May 2018target 2028
Blooming Grove Solar Energy Center
Solar
200 MWAgreement signed Livingston, ILPJM Sep 2018target 2028
Solar project J1062, Washtenaw County
Solar
200 MWAgreement signed Washtenaw, MIMISO Mar 2018target 2023
Solar project GEN-2018-050, Caddo Parish County
Solar
200 MWAgreement signed Caddo Parish, LASPP May 2018target 2028
Solar + storage project Company 166, Clark County
Solar + storage
200 MWAgreement signed Clark, NVWest Sep 2018target 2026
Solar project J1087, Scott County
Solar
200 MWUnder construction Scott, MOMISO Mar 2018target 2023
Battery storage project 60, Pierce County
Battery storage
200 MWAgreement signed Pierce, WAWest Aug 2018target 2028
Lower Crossing Wind
Onshore wind
200 MWPaused / redesign Kankakee, ILPJM Jan 2018target 2026
Onshore wind project GEN-2018-089, Castro County
Onshore wind
196 MWAgreement signed Castro, TXSPP Nov 2018target 2028
Solar project J1063, Clinton County
Solar
195 MWUnder construction Clinton, INMISO Mar 20182024
Horseshoe Solar
Solar ยท Horseshoe Solar Energy LLC
180 MWIn study Livingston, NYNYISO May 2018target 2028
Kettle Solar One
Solar + storage
180 MWAgreement signed San Diego, CACAISO Apr 2018target 2026
Solar project MPC03600, Richland County
Solar
170 MWAgreement signed Richland, NDMISO May 2018target 2027
Solar project G0602, Grant County
Solar
170 MWIn study Grant, WAWest Oct 2018target 2022
Fagus Solar Park 1 SLF
Solar + storage ยท Excel Advantage Services, LLC dba Misae Solar Park II
166 MWAgreement signed Childress, TXERCOT May 2018target 2026
CAROL wind
Onshore wind
165 MWPaused / redesign Potter, TXERCOT Dec 2018target 2024
Solar project GEN-2018-106, Caddo Parish County
Solar
165 MWAgreement signed Caddo Parish, LASPP Nov 2018target 2028
Solar project J1174, Worth County
Solar
165 MWUnder construction Worth, IAMISO Mar 2018target 2024
Onshore wind project J1175, Worth County
Onshore wind
165 MWAgreement signed Worth, IAMISO Mar 2018target 2024
Janus
Solar + storage
164 MWAgreement signed Colusa, CACAISO Apr 2018target 2026
Golden Aster Solar Energy Center
Solar
160 MWPaused / redesign Grant, INPJM Sep 2018target 2026
Battery storage project GEN-2018-072, Kay County
Battery storage
151 MWAgreement signed Kay, OKSPP Oct 2018target 2027
Battery storage project GEN-2018-071, Kay County
Battery storage
151 MWAgreement signed Kay, OKSPP Oct 2018target 2027
Solar project GEN-2018-003, Bowie County
Solar
150 MWAgreement signed Bowie, TXSPP Apr 2018target 2027
Solar project 2019-G3
Solar
150 MWAgreement signed West Dec 2018target 2021
Harvey Solar I
Solar
150 MWAgreement signed Licking, OHPJM Mar 2018target 2028
Solar project J1027, Pike County
Solar
150 MWAgreement signed Pike, INMISO Mar 2018target 2022
Energy Mountain
Battery storage
150 MWPaused / redesign Bucks, PAPJM Mar 2018target 2029

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)