🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR · SPP

Solar project GEN-2018-003, Bowie County

Solar project GEN-2018-003, Bowie County is a 150 MW solar request with a signed interconnection agreement in the SPP interconnection queue, in Bowie County, Texas, connecting to AEP.

Queue statusConsented
  1. PlanningQueued Apr 2018 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2018-003
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
North Boston-Bann 138kV Line
Location
Bowie County, Texas
Technology
Solar: 150 MW
Total requested
150 MW
Service type
NRIS and ERIS
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
25 April 2018
Proposed online date
June 2027

Location

Marker shows the centre of Bowie County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Bowie County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem