United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR + STORAGE Β· SPP

Solar + storage project GEN-2023-080, Bowie County

Solar + storage project GEN-2023-080, Bowie County is a 200 MW solar + storage request withdrawn in the SPP interconnection queue, in Bowie County, Texas, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2023 (completed)
  2. Withdrawn / abandonedApr 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2023-080
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Lydia - Northwest Texarkana 345 kV
Location
Bowie County, Texas
Technology
Solar: 200 MW Β· Battery
Total requested
200 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
2 October 2023
Proposed online date
December 2028
Withdrawn
April 2024

Location

Marker shows the centre of Bowie County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Bowie County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem