SOLAR · WESTSolar project 2019-G3
Solar project 2019-G3 is a 150 MW solar request with a signed interconnection agreement in the West interconnection queue, connecting to WAPA Rocky Mountain Region.
Queue statusConsented
- PlanningQueued Dec 2018 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2021 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 2019-G3
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- WAPA Rocky Mountain Region
- Connection point (POI)
- Ault 345-kV
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Study phase
- Executed LGIA
- Queue status
- Active
- Entered queue
- 12 December 2018
- Proposed online date
- December 2021
Location
No county location in the queue data.