🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

SOLAR · WEST

Solar project 2019-G3

Solar project 2019-G3 is a 150 MW solar request with a signed interconnection agreement in the West interconnection queue, connecting to WAPA Rocky Mountain Region.

Queue statusConsented
  1. PlanningQueued Dec 2018 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2021 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
2019-G3
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA Rocky Mountain Region
Connection point (POI)
Ault 345-kV
Technology
Solar: 150 MW
Total requested
150 MW
Study phase
Executed LGIA
Queue status
Active
Entered queue
12 December 2018
Proposed online date
December 2021

Location

No county location in the queue data.

Power plants in · Transmission lines in