BATTERY STORAGE · NYISO

Kce NY 2

Kce NY 2 is a 200 MW battery storage request in interconnection study in the NYISO interconnection queue, in Montgomery County, New York, connecting to CHG&E.

Queue statusIn planning
  1. PlanningQueued Jan 2018 (current stage)
  2. ConsentedMar 2021 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
683
Grid region
NYISO (New York)
Utility / transmission owner
CHG&E
Developer
KCE NY 2, LLC
Connection point (POI)
Coldenham 115kV
Location
Montgomery County, New York
Technology
Battery: 200 MW
Total requested
200 MW
Study phase
SRIS, FS
Queue status
Active
Entered queue
18 January 2018
Agreement signed
16 March 2021
Proposed online date
June 2027

Location

Marker shows the centre of Montgomery County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Montgomery County