United States › Grid › Interconnection queues › New York

SOLAR + STORAGE · NYISO

Mill Point Solar

Mill Point Solar is a 250 MW solar + storage request in interconnection study in the NYISO interconnection queue, in Montgomery County, New York, connecting to NM-NG.

Queue statusIn planning
  1. PlanningQueued Jun 2020 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
1031
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
ConnectGen Montgomery County LLC
Connection point (POI)
Marcy - New Scotland 345kV
Location
Montgomery County, New York
Technology
Solar: 250 MW · Battery
Total requested
250 MW
Study phase
SRIS, FS
Queue status
Active
Entered queue
18 June 2020
Proposed online date
December 2028

Location

Marker shows the centre of Montgomery County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Montgomery County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem