🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Nebraska

SOLAR · SPP

Solar project GEN-2018-132, Pierce County

Solar project GEN-2018-132, Pierce County is a 202 MW solar request with a signed interconnection agreement in the SPP interconnection queue, in Pierce County, Nebraska, connecting to NPPD.

Queue statusConsented
  1. PlanningQueued Nov 2018 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2018-132
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
NPPD
Connection point (POI)
Antelope - Hoskins 345 kV
Location
Pierce County, Nebraska
Technology
Solar: 202 MW
Total requested
202 MW
Service type
NRIS and ERIS
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
21 November 2018
Proposed online date
December 2026

Location

Marker shows the centre of Pierce County; the queue data does not give exact sites.

Power plants in Nebraska · Transmission lines in Nebraska

Other requests in Pierce County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem