Withdrawn queue requests in North Dakota — page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown28555.0 GW
Active in queue14.5 GW63 requests
Agreement signed2,129 MW13 requests
Withdrawn28555.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

285 requests · page 3 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project J2772, Mercer County
Solar + storage
200 MWWithdrawn / abandoned Mercer, NDMISO Sep 2022target 2027
Battery storage project GEN-2022-245, Kidder County
Battery storage
200 MWWithdrawn / abandoned Kidder, NDSPP Mar 2022target 2028
Onshore wind project GI-0928, Mercer County
Onshore wind
200 MWWithdrawn / abandoned Mercer, NDWest Oct 2009target 2012
Onshore wind project GI-0905, Ward County
Onshore wind
200 MWWithdrawn / abandoned Ward, NDWest Feb 2009target 2012
Onshore wind project J780, Sheridan County
Onshore wind
200 MWWithdrawn / abandoned Sheridan, NDMISO Nov 2016target 2020
Solar project J1544, Morton County
Solar
200 MWWithdrawn / abandoned Morton, NDMISO Jun 2020target 2023
Onshore wind project J1754, Mchenry County
Onshore wind
200 MWWithdrawn / abandoned Mchenry, NDMISO Jun 2020target 2023
Onshore wind project J013, Stutsman County
Onshore wind
200 MWWithdrawn / abandoned Stutsman, NDMISO Jan 2009target 2012
Solar project GEN-2024-225, Kidder County
Solar
200 MWWithdrawn / abandoned Kidder, NDSPP Mar 2025target 2030
Solar project GEN-2023-031, Mclean County
Solar
200 MWWithdrawn / abandoned Mclean, NDSPP Oct 2023target 2028
Onshore wind project H084, Mclean County
Onshore wind
200 MWWithdrawn / abandoned Mclean, NDMISO Jul 2008target 2010
Onshore wind project GI-0904, Burleigh County
Onshore wind
200 MWWithdrawn / abandoned Burleigh, NDWest Jan 2009target 2012
Onshore wind project G751, Adams County
Onshore wind
200 MWWithdrawn / abandoned Adams, NDMISO Feb 2007target 2009
Onshore wind project J090, Mercer County
Onshore wind
200 MWWithdrawn / abandoned Mercer, NDMISO Oct 2009target 2012
Solar project J1852, Cass County
Solar
200 MWWithdrawn / abandoned Cass, NDMISO Jun 2022target 2025
Solar project J1428, Cass County
Solar
200 MWWithdrawn / abandoned Cass, NDMISO Apr 2019target 2022
Solar project GEN-2021-008, Mckenzie County
Solar
200 MWWithdrawn / abandoned Mckenzie, NDSPP May 2021target 2030
Onshore wind project MPC01700, Barnes County
Onshore wind
200 MWWithdrawn / abandoned Barnes, NDMISO Dec 2008target 2012
Onshore wind project J743, Cass County
Onshore wind
200 MWWithdrawn / abandoned Cass, NDMISO Jun 2017target 2020
Onshore wind project MPC01500, Pembina County
Onshore wind
200 MWWithdrawn / abandoned Pembina, NDMISO Jul 2008target 2010
Onshore wind project G713, Dickey County
Onshore wind
200 MWWithdrawn / abandoned Dickey, NDMISO Dec 2006target 2008
Onshore wind project G757, Adams County
Onshore wind
200 MWWithdrawn / abandoned Adams, NDMISO May 2011target 2009
Onshore wind project MPC02300, Grand Forks County
Onshore wind
200 MWWithdrawn / abandoned Grand Forks, NDMISO Jun 2009target 2018
Battery storage project J2518, Lamoure County
Battery storage
200 MWWithdrawn / abandoned Lamoure, NDMISO Sep 2022target 2024
Onshore wind project J511, Oliver County
Onshore wind
200 MWWithdrawn / abandoned Oliver, NDMISO Nov 2015target 2017
Onshore wind project J081, Mercer County
Onshore wind
200 MWWithdrawn / abandoned Mercer, NDMISO Oct 2009target 2011
Onshore wind project MPC01900, Cass County
Onshore wind
200 MWWithdrawn / abandoned Cass, NDMISO Apr 2008target 2012
Onshore wind project G885, Barnes County
Onshore wind
200 MWWithdrawn / abandoned Barnes, NDMISO Oct 2007target 2011
Battery storage project GEN-2024-185, Mckenzie County
Battery storage
199 MWWithdrawn / abandoned Mckenzie, NDSPP Mar 2025target 2029
Battery storage project GEN-2024-191, Mercer County
Battery storage
199 MWWithdrawn / abandoned Mercer, NDSPP Mar 2025target 2028
Battery storage project GEN-2024-192, Mercer County
Battery storage
199 MWWithdrawn / abandoned Mercer, NDSPP Mar 2025target 2028
Onshore wind project J897, Grand Forks County
Onshore wind
190 MWWithdrawn / abandoned Grand Forks, NDMISO Jun 2017target 2024
Onshore wind project J1961, Cass County
Onshore wind
190 MWWithdrawn / abandoned Cass, NDMISO Aug 2021target 2026
Solar project GEN-2022-018, Dunn County
Solar
186 MWWithdrawn / abandoned Dunn, NDSPP Jun 20222025
Onshore wind project GEN-2022-037, Williams County
Onshore wind
181 MWWithdrawn / abandoned Williams, NDSPP Jun 20222025
Onshore wind project G221, Dickey County
Onshore wind
180 MWWithdrawn / abandoned Dickey, NDMISO Apr 2002target 2005
Solar project GEN-2022-078, Bowman County
Solar
180 MWWithdrawn / abandoned Bowman, NDSPP Sep 2022target 2028
Onshore wind project J1888, Oliver County
Onshore wind
175 MWWithdrawn / abandoned Oliver, NDMISO Jan 2022target 2024
Battery storage project J3266, Sargent County
Battery storage
175 MWWithdrawn / abandoned Sargent, NDMISO Apr 2024target 2028
Onshore wind project GEN-2023-192, Lamoure County
Onshore wind
175 MWWithdrawn / abandoned Lamoure, NDSPP Oct 2023target 2030
Onshore wind project GI-1007, Mercer County
Onshore wind · Antelope Hills Wind
173 MWWithdrawn / abandoned Mercer, NDWest Aug 2010target 2016
Onshore wind project J1187, Mercer County
Onshore wind
152 MWWithdrawn / abandoned Mercer, NDMISO Mar 2018target 2022
Onshore wind project MPC02800, Cass County
Onshore wind
152 MWWithdrawn / abandoned Cass, NDMISO May 2016target 2017
Onshore wind project G359, Dickey County
Onshore wind
150 MWWithdrawn / abandoned Dickey, NDMISO Mar 20042020
Onshore wind project G624, Mcintosh County
Onshore wind
150 MWWithdrawn / abandoned Mcintosh, NDMISO Apr 2006target 2007
Onshore wind project H088, Sargent County
Onshore wind
150 MWWithdrawn / abandoned Sargent, NDMISO Jul 2008target 2010
Onshore wind project J880, Ward County
Onshore wind
150 MWWithdrawn / abandoned Ward, NDMISO Jun 2017target 2020
Gas project GI-1413, Mercer County
Gas
150 MWWithdrawn / abandoned Mercer, NDWest Sep 2014target 2017
Onshore wind project J607, Logan County
Onshore wind
150 MWWithdrawn / abandoned Logan, NDMISO May 2016target 2018
Onshore wind project J218, Adams County
Onshore wind
150 MWWithdrawn / abandoned Adams, NDMISO Jun 2011target 2012

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)