πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

BATTERY STORAGE Β· SPP

Battery storage project GEN-2024-192, Mercer County

Battery storage project GEN-2024-192, Mercer County is a 199 MW battery storage request withdrawn in the SPP interconnection queue, in Mercer County, North Dakota, connecting to BEPC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2025 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2024-192
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
BEPC
Connection point (POI)
Antelope Valley - Leland Olds 345 kV Line
Location
Mercer County, North Dakota
Technology
Battery: 199 MW
Total requested
199 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
1 March 2025
Proposed online date
December 2028

Location

Marker shows the centre of Mercer County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Mercer County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem