Solar project GEN-2019-037, Mercer County

Solar project GEN-2019-037, Mercer County is a 150 MW solar request with a signed interconnection agreement in the SPP interconnection queue, in Mercer County, North Dakota, connecting to BEPC.

Queue statusConsented
  1. PlanningQueued May 2019 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2023 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2019-037
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
BEPC
Connection point (POI)
Leland Olds 345kV substation
Location
Mercer County, North Dakota
Technology
Solar: 150 MW
Total requested
150 MW
Service type
NRIS and ERIS
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
17 May 2019
Proposed online date
December 2023

Location

Marker shows the centre of Mercer County; the queue data does not give exact sites.

Power plants in North Dakota · Transmission lines in North Dakota

Other requests in Mercer County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem