United States › Grid › Interconnection queues › North Dakota

GAS · SPP

Gas project ERAS-2025-011, Mercer County

Gas project ERAS-2025-011, Mercer County is a 750 MW gas request in interconnection study in the SPP interconnection queue, in Mercer County, North Dakota, connecting to BEPC.

Queue statusIn planning
  1. PlanningQueued Oct 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
ERAS-2025-011
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
BEPC
Connection point (POI)
Leland Olds 345kV Substation
Location
Mercer County, North Dakota
Technology
Gas: 750 MW
Total requested
750 MW
Service type
NRIS and ERIS
Study phase
ERAS
Queue status
Active
Entered queue
1 October 2025
Proposed online date
September 2030

Location

Marker shows the centre of Mercer County; the queue data does not give exact sites.

Power plants in North Dakota · Transmission lines in North Dakota

Other requests in Mercer County