πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

SOLAR Β· SPP

Solar project GEN-2021-072, Mercer County

Solar project GEN-2021-072, Mercer County is a 600 MW solar request withdrawn in the SPP interconnection queue, in Mercer County, North Dakota, connecting to BEPC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2021 (completed)
  2. Withdrawn / abandonedSep 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2021-072
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
BEPC
Connection point (POI)
345kV Transmission Line from Antelope Valley to Leland Olds Substation
Location
Mercer County, North Dakota
Technology
Solar: 600 MW
Total requested
600 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
19 May 2021
Proposed online date
December 2027
Withdrawn
September 2024

Location

Marker shows the centre of Mercer County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Mercer County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem