United States βΊ Grid βΊ Interconnection queues βΊ North Dakota
ONSHORE WIND Β· MISOOnshore wind project H088, Sargent County
Onshore wind project H088, Sargent County is a 150 MW onshore wind request withdrawn in the MISO interconnection queue, in Sargent County, North Dakota.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2008 (completed)
- Withdrawn / abandonedAug 2010 (project stopped here)
- ConsentedAug 2010 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- H088
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- OTP Forman 230kV Substation
- Location
- Sargent County, North Dakota
- Technology
- Wind: 150 MW
- Total requested
- 150 MW
- Study phase
- SPA - SIS
- Queue status
- Withdrawn
- Entered queue
- 15 July 2008
- Agreement signed
- 12 August 2010
- Proposed online date
- December 2010
- Withdrawn
- August 2010
Location
Marker shows the centre of Sargent County; the queue data does not give exact sites.
Power plants in North Dakota Β· Transmission lines in North Dakota
Other requests in Sargent County
- Battery storage project GEN-2024-034, Sargent CountyBattery storage Β· 175 MW Β· in study
- Battery storage project J2913, Sargent CountyBattery storage Β· 90.0 MW Β· in study
- Battery storage project J3266, Sargent CountyBattery storage Β· 175 MW Β· withdrawn
- Battery storage project J2094, Sargent CountyBattery storage Β· 100 MW Β· withdrawn
- Battery storage project J2896, Sargent CountyBattery storage Β· 80.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem