BATTERY STORAGE Β· MISO

Battery storage project J3266, Sargent County

Battery storage project J3266, Sargent County is a 175 MW battery storage request withdrawn in the MISO interconnection queue, in Sargent County, North Dakota, connecting to OTTER TAIL POWER COMPANY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2024 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3266
Grid region
MISO (Midcontinent)
Utility / transmission owner
OTTER TAIL POWER COMPANY
Connection point (POI)
Forman 230 kV Substation
Location
Sargent County, North Dakota
Technology
Battery: 175 MW
Total requested
175 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Withdrawn
Entered queue
11 April 2024
Proposed online date
August 2028
Withdrawn
December 2025

Location

Marker shows the centre of Sargent County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Sargent County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem