United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

BATTERY STORAGE Β· MISO

Battery storage project J2896, Sargent County

Battery storage project J2896, Sargent County is a 80.0 MW battery storage request withdrawn in the MISO interconnection queue, in Sargent County, North Dakota, connecting to OTTER TAIL POWER COMPANY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedMar 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2896
Grid region
MISO (Midcontinent)
Utility / transmission owner
OTTER TAIL POWER COMPANY
Connection point (POI)
Gwinner 115kV Substation
Location
Sargent County, North Dakota
Technology
Battery: 80.0 MW
Total requested
80.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
14 September 2022
Proposed online date
April 2025
Withdrawn
March 2023

Location

Marker shows the centre of Sargent County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Sargent County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem