ONSHORE WIND Β· WEST

Onshore wind project GI-0904, Burleigh County

Onshore wind project GI-0904, Burleigh County is a 200 MW onshore wind request withdrawn in the West interconnection queue, in Burleigh County, North Dakota, connecting to WAPA/BEPC/HCPD Integrated System.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2009 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GI-0904
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA/BEPC/HCPD Integrated System
Connection point (POI)
Bismarck 115kV
Location
Burleigh County, North Dakota
Technology
Wind: 200 MW
Total requested
200 MW
Service type
NRIS and ERIS
Study phase
IAP
Queue status
Withdrawn
Entered queue
22 January 2009
Proposed online date
December 2012

Location

Marker shows the centre of Burleigh County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Burleigh County