🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › North Dakota

ONSHORE WIND · WEST

Onshore wind project GI-0615, Burleigh County

Onshore wind project GI-0615, Burleigh County is a 50.0 MW onshore wind request built and operating in the West interconnection queue, in Burleigh County, North Dakota, connecting to WAPA/BEPC/HCPD Integrated System.

Queue statusOperating
  1. PlanningQueued Oct 2006 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Sep 2008 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GI-0615
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA/BEPC/HCPD Integrated System
Developer
Wilton Wind II, LLC
Connection point (POI)
Hilken 230kV [Ecklund 230kV]
Location
Burleigh County, North Dakota
Technology
Wind: 50.0 MW
Total requested
50.0 MW
Service type
NRIS and ERIS
Study phase
IAE/IS
Queue status
Operational
Entered queue
18 October 2006
Proposed online date
September 2008

Location

Marker shows the centre of Burleigh County; the queue data does not give exact sites.

Power plants in North Dakota · Transmission lines in North Dakota

Other requests in Burleigh County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem