United States › Grid › Interconnection queues › North Dakota
ONSHORE WIND · WESTOnshore wind project GI-0715, Burleigh County
Onshore wind project GI-0715, Burleigh County is a 100 MW onshore wind request built and operating in the West interconnection queue, in Burleigh County, North Dakota, connecting to WAPA/BEPC/HCPD Integrated System.
Request details
- Queue ID
- GI-0715
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- WAPA/BEPC/HCPD Integrated System
- Developer
- Baldwin Wind, LLC
- Connection point (POI)
- Hilken 230kV [Ecklund 230kV]
- Location
- Burleigh County, North Dakota
- Technology
- Wind: 100 MW
- Total requested
- 100 MW
- Service type
- NRIS and ERIS
- Study phase
- IAE/IS
- Queue status
- Operational
- Entered queue
- 2 July 2007
- Proposed online date
- October 2010
Location
Marker shows the centre of Burleigh County; the queue data does not give exact sites.
Power plants in North Dakota · Transmission lines in North Dakota
Other requests in Burleigh County
- Onshore wind project GI-0615, Burleigh CountyOnshore wind · 50.0 MW · built
- Onshore wind project GI-0508, Burleigh CountyOnshore wind · 50.0 MW · built
- Onshore wind project G861, Burleigh CountyOnshore wind · 960 MW · withdrawn
- Onshore wind project G860, Burleigh CountyOnshore wind · 900 MW · withdrawn
- Onshore wind project J580, Burleigh CountyOnshore wind · 298 MW · withdrawn
- Onshore wind project GEN-2016-035, Burleigh CountyOnshore wind · 265 MW · withdrawn
- Onshore wind project GI-0904, Burleigh CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project MPC01800, Burleigh CountyOnshore wind · 140 MW · withdrawn
- Onshore wind project GI-0924, Burleigh CountyOnshore wind · 136 MW · withdrawn
- Onshore wind project J940, Burleigh CountyOnshore wind · 100 MW · withdrawn
- Onshore wind project J178, Burleigh CountyOnshore wind · 99.6 MW · withdrawn
- Onshore wind project GI-0727, Burleigh CountyOnshore wind · 99.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem